Four laning of Chowka to Kaimaha near MP/UP Border section NH‐34 from Design Ch. 145+000 to Design Ch. 197+266 excluding existing Chhatarpur bypass from Design Ch. 160+307 to Design Ch. 168+630 (length – 8.323 km) (Total length – 43.924 km) (Pkg‐IV) in the State of Madhya Pradesh on Hybrid Annuity Mode.

The National Highway Authority of India (NHAI) has been entrusted with the assignment of Development of Economic Corridors, Inter-Corridors, Feeder Routes and Coastal Roads primarily to improve freight movement in the Country. The ECONOMIC CORRIDOR Pkg-IV project road NH-34 (Old NH-86) starts at (Design chainage 145+000) near Chowka village and ends at Kaimaha at km 197+226 of NH 34 (Design chainage 197+266). The existing project road is predominantly a 2 -Lane Road with Paved Shoulder. The existing ROW is encroached and squatted at various locations specifically in existing Villages/marketplaces. It traverses through Chowka, Niwari, Chattarpur, Gadi Malhera, Ujara Villages/towns of Chhatarpur District, in the state of Madhya Pradesh. Total length of the existing project road is about 44.235km. (Design Length = 43.924 km)

PROJECT AT GLANCE

Bid Project Cost:

Rs. 586.66 Cr.

Project Start Date:

22.09.2025

Project Execution Period:

2 Years (730 Days)

Operation & Maintenance:

15 Years

Length of the Project Highway:

43.924 km

Client:

National Highways Authority of India
.

Concessionaire:

MKC Chhatarpur Bypass PKG-4 Mahakaleshwar Highways Pvt. Ltd.

Independent Engineer:

M/s Chaitanya Projects Consultancy Ltd. In JV With M/S Geo Design and Research Pvt. Ltd.

Lenders:

State Bank of India

Lenders’ Independent Engineer:

Goldrush Capital Services Private Limited

PROPOSAL FOR IMPROVED CONNECTIVITY

This ambitious project aims to build and upgrade National Highways and Expressways across India. In Madhya Pradesh, the Bharatmala Project focuses on improving connectivity to improve freight movement in India, including constructing new highways and bridges to reduce travel time and boost economic activities.

PROJECT TIMELINE

  • 03.01.2025
    Letter Of Award
  • 19.02.2025 Concession Agreement
  • 09.07.2025 Financial Closure
  • 22.09.2025 Appointed Date
  • 22.09.2027 Schedule Completion Date
  • (15 Years)
    O & M Period

PROJECT SITE

The ECONOMIC CORRIDOR Pkg-IV project road NH-34 (Old NH-86) starts at (Design chainage 145+000) near Chowka village and ends at Kaimaha at km 197+226 of NH section in the State of Madhya Pradesh. The construction package for the project includes developing the existing two lane carriageway to four lane from Chowka village to Kaimaha by constructing new alignment for faster congestion free connectivity. An Index Map and location Map of the Project highway is given as below:

MONTHLY PROGRESS REPORT