Widening to 4 lanes from km. 139.00 to km. 179.20 of NH-135A Pkg-III (Jaunpur – Akbarpur section) in on Hybrid Annuity Mode in the state of Uttar Pradesh

The Government of India had entrusted to the Authority the development, maintenance and management of National Highway No.135 A including the section from Jaunpur to Akbarpur (From km. 139.00 to km 179.20). The Authority had resolved Widening to 4 lane from km. 139.00, to km 179.20 of NH-135A Pkg-III (Jaunpur – Akbarpur Section) and Akbarpur Bypass in the state of Uttar Pradesh (approximately 44.514 km by Four -Laning thereof (the “Project”) on design, build, operate and transfer (the “DBOT Annuity” or “Hybrid Annuity”) in the state of Uttar Pradesh.
PROJECT AT GLANCE
Bid Project Cost: |
Rs. 633.13 Cr. |
Project Start Date: |
16.01.2026 |
Project Execution Period: |
2 Years |
Operation & Maintenance: |
15 Years |
Length of the Project Highway: |
44.514 km |
Client: |
Ministry of Road Transport & Highways |
Concessionaire: |
MKC Jaunpur – Akbarpur Kashivishwanathji (Pkg-3) Highway Pvt. Ltd. |
Independent Engineer: |
Technocrats Advisory Services Pvt. Ltd. |
Lenders: |
Indian Bank & Bank of India |
Lenders’ Independent Engineer: |
Goldrush Capital Services Pvt. Ltd. |
PROPOSAL FOR IMPROVED CONNECTIVITY
This ambitious project aims to build and upgrade National Highways and Expressways across India. in Uttar Pradesh, the Bharatmala Project focuses on improving connectivity, including constructing new highways and bridges to reduce travel time and boost economic activities.
PROJECT TIMELINE
- 13.03.2024 Letter of Award
- 06.06.2024 Concession Agreement
- 25.10.2024 Financial Closure
- 16.01.2026 Appointed Date
- 15.01.2028 Schedule Completion Date
- (15 Years) O & M Period
PROJECT SITE
The proposed alignment starts from Existing Chainage Km 113+500/Design Chainage km. 139.000 (Takha West considered) and ends at km 153+530/Design Chainage km. 179.200 (Shahzad Pur near Police Chowki,) of NH 135A and Akbarpur Bypass of 4.31 km length. The existing length of project road is 40.03 km and design length are 44.514 km which include Akbarpur bypass. Project road runs in plain terrain in its entire length. Project Highway shall include the land. buildings, structures and road works. By constructing new alignment for faster congestion free connectivity. An Index Map and location Map of the Project highway is given as below:
: