Widening to 4 lanes from km. 108.50 to km. 139.00 of NH-135A Pkg-II (Jaunpur – Akbarpur section) in on Hybrid Annuity Mode in the state of Uttar Pradesh

PROJECT AT GLANCE

Bid Project Cost:

Rs. 569.66 Cr.

Project Start Date:

30-03-2025

Project Execution Period:

730 Days from Appointed Date.

Operation & Maintenance:

15 Years commencing from COD

Length of the Project Highway:

30.500 Km

Client:

Ministry of Road Transport & Highways

Concessionaire:

M/s MKC Jaunpur – Akbarpur Kashivishwanathji (Pkg-2) Highway Pvt. Ltd.

Independent Engineer:

M/s Technocrats Advisory Services Pvt. Ltd.

PROJECT TIMELINE

  • 13.03.2024
    Letter Of Award
  • 06.06.2024 Agreement
  • 25.10.2024 Financial Closure
  • 30.03.2025 Appointed Date
  • 29th March 2027 Schedule Completion Date
  • (15 Years)
    O & M Period

MONTHLY PROGRESS REPORT

No. Month Remarks
1 MAY-25