UP-GRADATION & FOUR LANING OF POANTA SAHEB-BALLUPUR SECTION OF NH-72 IN THE STATE OF UTTARAKHAND UNDER NH(O) ON HAM MODEL. PACKAGE-II: MEDINIPUR TO BALLUPUR (DEHRADUN) FROM DESIGN CH. 18.700 TO CH. 44.800.

The Government of India had entrusted to the Authority the development, maintenance and management of National Highway No. 72 including the section from Design Ch. 18.700 to Ch. 44.800 (approx. Design Length 26.100 km). The Authority had resolved to upgrade the existing road from Design Ch.l 8.700to Ch. 44.800(approximately 26.100 km) on the Poahta Saheb- Ballupur Section of National Highway No.- 72 (hereinafter called the “NH-72”) in the State of Uttarakhand by Four-Laning thereof (the “Project”) on design, build, operate and transfer (the “DBOT Annuity” or “Hybrid Annuity”).

PROJECT AT GLANCE

Bid Project Cost:

Rs. 516.56 Cr.

Project Start Date:

18-02-2023

Project Execution Period:

2 Years

Operation & Maintenance:

15 Years

Length of the Project Highway:

26.10 Km

Client:

National Highways Authority of India (NHAI)

Concessionaire:

MKC POANTA-SAHEB DEHRADUN KEDARNATHJI HIGHWAYS PVT. LTD.

Independent Engineer:

URS Scott Wilson India Pvt. Ltd. In JV with Lion Enginnering Consultants Pvt. Ltd.

Lenders:

State Bank of India

Lenders Independent Engineer:

FP Project Management (Formerly Frischmann prabhu (India) Private Limited)

PROPOSAL FOR IMPROVED CONNECTIVITY

The Medinipur to Ballupur project in Uttarakhand is a section of the Poanta Saheb-section of the old NH-72. The project’s purpose is to improve connectivity between Uttarakhand, Himachal Pradesh, and Chandigarh.

PROJECT TIMELINE

  • 30.05.2022 Letter of Award​
  • 14.07.2022 Agreement​
  • 12.01.2023 Financial Closure​
  • 18.02.2023 Appointed Date
  • 17.02.2025 Schedule Completion Date​
  • (15 Years) ​O & M Period​

Existing Project Site

The Existing Site of the Two Lane Project Highway comprises the section of National Highway 72 commencing from 18.700 to 44.800 i.e., Medinipur to Ballupur in Paonta Saheb-Ballupur section in the State of Uttrakhand. The construction package for the project includes developing the existing two lane carriageway to four lane from Medinipur existing km 18.700 to Ballupur existing km 44.800. By constructing new alignment for faster congestion free connectivity. An Index Map and location Map of the Project highway is given as below:

MONTHLY PROGRESS REPORT

No. Month Remarks
1 FEB-23
 
2 MAR-23
 
3 APR-23
 
4 MAY-23
 
5 JUN-23
 
6 JUL-23
 
7 AUG-23
 
8 SEP-23
 
9 OCT-23
 
10 NOV-23
 
11 DEC-23
 
12 JAN-24
 
13 FEB-24
 
14 MAR-24
 
15 APR-24
 
16 MAY-24
 
17 JUN-24
 
18 JUL-24
 
19 AUG-24
 
20 SEP-24
 
21 OCT-24
 
22 NOV-24